PPR Pipe Fitting Installation Manual

time2016/11/16

more knowledge of installing PPR pipe

PPR Pipe Fitting Installation Manual

 

Fusion


1 Mark the pipe
Mark the pipe for depth of penetration into the heater bush and fitting (see table). The mark must remain visible under heating and joining. 

2 Heat pipe & fitting
Push the pipe and the fitting into the heating tools. Once pipe and fitting are hot (after the correct time), pull out pipe and fitting very slowly.

3 Joint pipe & fitting
Joint the pipe & the fitting and push the pipe until it reaches the mark (that has to stay outside).
During the jointing time the welded part of pipe and fitting must remain fix, without any rotation.
During the cooling time, the welded part of pipe and fitting can be adjusted until cold. 

4 Fusion inspection
Fusion inspection. The outer fusion seam must be inspected. The seam must be present all around the pipe.


Summary Value table


Pipe Diameter(mm)Minimum wall
thickness (mm)
Insert depth (mm)Heating time (sec)Jointing time (sec)Cooling trime (sec)
203, 414642
254, 216743
325, 418864
406, 7201264
508, 4231865
6310, 5262586
7512, 5283088
9015, 03140108
11018, 43350108
PPR Pipe Cutting India

PPR Pipe Welding India

PPR Pipe Fitting Installation India


Minimum cooling time without 
moving sleeve and pipe

d mmminutes
2010
2510
3210
4015
5015
6320
7525
9030